Today, October 23, 2026, Lotte Eco Smart City Thu Thiem officially breaks ground according to the schedule announced by Lotte and Phat Dat. The project is located in Functional Area 2A, the core of Thu Thiem New Urban Area, now belonging to An Khanh Ward, HCMC.
Perspective rendering of Lotte Eco Smart City Thu Thiem
This is the land plot contracted in 2017 with a groundbreaking ceremony held in 2022. In 2025, the developer even submitted a request to pause the project. Nearly 10 years later, heavy machinery is finally operating on the site.
There is good news. But I'll be straightforward from the start: the items breaking ground today are the two commercial-service blocks, not the residential apartments. As of writing, the project has not been launched for sale and there is no official price list.
This article is tailored for expats and investors looking to buy, rent, or invest in Thu Thiem. I clearly separate official information, press reports, and Achieve Realty VN's personal market insights. Please evaluate accordingly.
Contact Achieve Realty VN:
📞 086 888 2539 - 096 669 2202
Quick Answer: On Oct 23, 2026, the project commences construction on blocks 2-1 and 2-3. These are the two commercial-service blocks fully developed by Phat Dat, with a total gross floor area (GFA) of about 171,580 sq.m. The estimated construction time is 36 months, meaning completion by late 2029 at the earliest. The residential component has not yet broken ground and is not open for sale.
The project is divided into 6 lots, denoted 2-1 to 2-6. Each lot has its own function and developer:
Why start with the commercial blocks? There is no official statement from the developer. Based on my deduction: office and commercial spaces do not require the strict "sales permit for off-plan properties" like residential units. Construction procedures are typically more streamlined. Please treat this as a personal assessment, not official news.
36 months is the planned timeline. For a project with multiple basements in the core of Thu Thiem, delays of a few quarters are standard market practice. I will update on the actual site progress as it happens.
Quick Answer: Lotte Eco Smart City Thu Thiem is located in Functional Area 2A, Thu Thiem New Urban Area, An Khanh Ward, HCMC. As of July 1, 2025, HCMC abolished the district level for Thu Duc City, so any listings still mentioning "District 2" or "Thu Duc City" are using the old address format.
Project location on the Thu Thiem New Urban Area map
This is a detail many websites get wrong. The correct current address only has two levels: An Khanh Ward – HCMC. Empire City, The Metropole, Zeit River, and The River are also located in An Khanh Ward.
Specific location of the land plot:
To help you visualize: if Empire City is the front-row seat looking across to District 1, Lotte Eco Smart City is sitting right behind the main stage, next to the plaza. This location trades a direct river view for extreme centrality. Which is more valuable depends on whether you are buying to live or for investment yields.
Quick Answer: According to the 4th Amended Investment Registration Certificate dated Sept 10, 2026, the project has a total land area of 74,513.4 sq.m (approx. 7.45 ha), comprising 6 lots (2-1 to 2-6). The total announced investment capital is about 60,000 billion VND. Upon completion, the project is expected to offer over 1,600 residential units along with offices, retail spaces, and hotels.
| Category | Announced Figures | Notes |
|---|---|---|
| Location | Functional Area 2A, An Khanh Ward, HCMC | Thu Thiem New Urban Area Core |
| Land Area | 74,513.4 sq.m (~7.45 ha) | Some articles cite 7.54 ha, likely a typo. I use the official IRC figure. |
| Number of lots | 6 lots (2-1 to 2-6) | Including traffic routes and technical infrastructure |
| Total Capital | ~60,000 billion VND | In 2017, it was approx. 20,100 billion VND |
| Residential Units | Over 1,600 units | Unit mix has not been announced |
| Office Space | Over 152,000 sq.m GFA | Grade A orientation |
| Commercial Space | ~50,000 sq.m GFA | |
| Hotels | Over 34,000 sq.m GFA | |
| Serviced Apartments | ~8,000 sq.m GFA | |
| Oct 23, 2026 Groundbreaking | Blocks 2-1 and 2-3 | ~171,580 sq.m GFA, 36 months |
The most notable figure is the capital: from 20,100 billion in 2017 up to about 60,000 billion in 2026, roughly a 3-fold increase. Most of this difference comes from the land use fee, which alone accounts for 17,569 billion VND.
The higher the land cost, the harder it is for the selling price to be cheap. This is a general market logic, not my specific price forecast.
Quick Answer: The legal entity executing the project is Lotte Properties HCMC Co., Ltd. Following the 2026 transaction, the equity structure consists of Lotte Shopping 30.59%, Hotel Lotte 22.94%, Lotte E&C 11.47%, and Phat Dat (PDR) 35%. MB Bank is financing the entirety of Phat Dat's capital contribution to the project.
Key milestones of the partnership:
Regarding the amount Phat Dat spent to acquire the 35% stake, newspapers have reported varying figures. I haven't found the original document to cross-check, so I won't include any numbers here.
A realistic perspective: Lotte has experience operating commercial properties and hotels; the Lotte Mart chain and Lotte Hotels have been in Vietnam for years. Phat Dat is a local enterprise, familiar with procedures, having just undergone a restructuring phase and selling off other projects to focus resources on Thu Thiem. This combination looks reasonable on paper. The actual effectiveness must be measured by the site progress over the next 12–24 months.
Quick Answer: The project faced hurdles regarding land valuation, legal procedures, and scale adjustments. The contract was signed in 2017, ground was broken in Sept 2022, but construction couldn't proceed. In Aug 2025, Lotte sent a document proposing termination. The deadlock was only resolved when Lotte fully paid the 17,569 billion VND land use fee on July 31, 2026.
Actual site progress / Groundbreaking ceremony on Oct 23, 2026
| Timeline | Event |
|---|---|
| July 25, 2017 | Lotte signed the project execution contract with HCMC People's Committee. Capital approx. 20,100 bil. VND. |
| 2018 | The City proposed downsizing from 10 lots to 6 lots due to site clearance difficulties. |
| Sept 2, 2022 | Groundbreaking ceremony, after receiving the land. The site mostly stood still afterward. |
| 2025 | Approved land price around 16,190 billion VND. |
| Aug 20, 2025 | Lotte Properties HCMC submitted a request to terminate the project contract. |
| Late 2025 | HCMC worked to resolve issues, and the project was retained. |
| June 26, 2026 | Lotte – Phat Dat investment cooperation signed. |
| July 31, 2026 | Completed payment of 17,569 billion VND in land use fees. |
| Sept 10, 2026 | 4th Amended Investment Registration Certificate issued. |
| Oct 23, 2026 | Commencement of blocks 2-1 and 2-3 (as planned). |
In Thu Thiem, a "groundbreaking ceremony" and "actual construction commencement" are two different things. The 2022 event was ceremonial: there was a stage and photos, but not enough permits to build. This time is different due to a decisive factor: the land fee is fully paid. With no pending financial obligations, the likelihood of the project stalling again is significantly lower than in 2022.
Lower doesn't mean zero. The project still needs building permits for each item, capital for each phase, and real construction progress. This 10-year history is why I advise expats and investors to look at the actual construction site, not just the 3D renderings.
👉 See the list of handed-over apartments with Pink Books in the Thu Thiem core currently available at Achieve Realty VN → Click Here
Quick Answer: No. As of Oct 23, 2026, Lotte Eco Smart City Thu Thiem has not opened for sale and has not announced apartment prices. The residential portion in lots 2-2, 2-4, and 2-6 has not broken ground. All "estimated price lists" or "priority bookings" circulating currently have no official basis.
Following today's groundbreaking news, I anticipate many rumors about "taking bookings," "free reservations," or "F0 prices from...". You need to grasp three things:
These are prices of other projects that are already built or nearing handover. This is not a price forecast for Lotte.
An additional note: the project is heavily oriented towards Grade A offices and hotels. Apartments here will likely share the dense, fast-paced urban rhythm of a commercial-office hub. Those who prefer a quiet, riverside resort lifestyle should consider carefully once the detailed designs are available.
Quick Answer: In the short term, the groundbreaking mainly affects market sentiment, as the Thu Thiem core gets another actively moving puzzle piece. The real impact on rental yields and housing demand will only become clear when the office-commercial blocks go into operation, earliest around 2029–2030.
I divide the impact into three layers for easier understanding:
For genuine tenants, especially families with young children, you should carefully ask about the unit's orientation and wind direction before signing a lease. In summary, Lotte breaking ground is good news for Thu Thiem's long-term picture. But it won't turn your apartment into cash tomorrow.
Quick Answer: Ready: Thu Thiem Tunnel, Ba Son Bridge, the central plaza, and core roads. Proposed: Thu Thiem – Long Thanh metro line connecting to Long Thanh Airport, and the metro extension into Thu Thiem. Articles claiming it's "right at the metro station" are describing planning, not operational stations.
Here is the breakdown:
✅ Ready for daily use
⏳ On paper or in preparation
Why do I separate these so carefully? In Thu Thiem, the word "soon" has stretched for a decade. You should price properties based on what exists today. Future infrastructure should only be considered a bonus; don't pay in advance for it.
Quick Answer: Those needing to live in or rent out immediately should choose handed-over projects with pink books in the Thu Thiem core. Those wanting to buy Lotte apartments should wait for official sales info and absolutely not pay deposits through unclear legal channels. Long-term investors can track the commercial block's progress as an indicator for the whole area.

Quick Answer: There are four main risks. The 36-month schedule is merely a plan. The residential portion lacks a start date. The estimated 60,000 billion VND capital is massive. Surrounding residents will suffer from construction impacts. None of these make it a "bad" project, but they must be factored into your decision.
Q: When does Lotte Eco Smart City Thu Thiem break ground?
October 23, 2026, according to Lotte and Phat Dat's plan. The components starting are commercial blocks 2-1 and 2-3.
Q: What is the current address of Lotte Eco Smart City Thu Thiem?
Functional Area 2A, Thu Thiem New Urban Area, An Khanh Ward, HCMC.
Q: How many apartments does Lotte Eco Smart City have?
According to announced info, the project is expected to provide over 1,600 residential units. The unit mix has not yet been announced.
Q: When will Lotte Eco Smart City Thu Thiem open for sale, and what is the price?
As of Oct 23, 2026, it has not opened for sale and prices are not announced.
Q: When will the commercial blocks be finished?
The construction plan is 36 months from groundbreaking, meaning around late 2029 if on schedule.
For me, the most valuable point today isn't the groundbreaking ceremony. It lies in the 17,569 billion VND paid into the state budget since July. Ceremonies happened in 2022 too. But the land fee being fully settled—this is a first.
Lotte Eco Smart City is good news for the entire Thu Thiem core. A massive empty plot is finally seeing construction. A significant office, retail, and hotel block will form right next to the central plaza.
However, good news for the area is different from a reason to drop your money today. If you need a real place to live or real cash flow, completed projects nearby remain the tangible choices. If you want an apartment in Lotte, patiently wait for the sales permits. If anyone urges you to transfer money before that day, just ask them one question: "Where is the sales eligibility permit from the Department of Construction?"
Achieve Realty VN will monitor the site and provide updates when official information regarding the residential component becomes available. Trust builds everything, and trust begins by not predicting things that don't exist yet.
Achieve Realty VN
Level 10, Miss Ao Dai Building, 21 Nguyen Trung Ngan, Ben Nghe Ward, Ho Chi Minh City, Vietnam
Hotline: 086 888 2539 | 096 669 2202
Email: sales@achievereal.com
* Information updated on Oct 23, 2026, based on announcements from the developer and the press. Reference prices for neighboring projects are based on the May 2026 market basket; please re-verify before executing any transactions.
```eof